John Holland has been engaged by Transport of NSW to deliver the first phase of the Parramatta Light Rail Stage 2 with the Enabling Works to construct the first 1.3kms of new light rail, including a public and active transport bridge over the Parramatta River between Wentworth Point and Melrose Park.
During December, the project will be progressing with the following works to prepare for bridge construction:
- Completion of Viva high-pressure pipeline on Wharf Road and preparing for the next stages to commence on Mary Street and Andrew Street in the new year
- Ongoing structural piling activities
- Utility investigation activities will occur on Hill Road, Waratah Street and Mary Street, along with continuing the removal of the decommissioned transmission tower in Melrose Park.
ποΈ Upcoming site closure
Melrose Park and Wentworth Point construction sites will be closed for the holiday period from Saturday, 20 December 2025 until Sunday, 4 January 2026 and will be returning on Monday, 5 January.
π€ Ermington Boat Ramp will be open during the above site closure period.
Click hereΒ to view our planned activities or visit our project webpage